Method Statement for Formwork, Reinforcement and Concrete Works

Method Statement for Form-work, Reinforcement and Concrete Works | Construction Engineering

SCOPE:

This procedure is developed for the construction execution of form, reinforcement, and concrete works for _____ (Project Name) at _____ (City Name). The latest revision of the project specifications shall be used as references and is part of this Method Statement in the execution of work.

 

Method Statement for Form-work, Reinforcement and Concrete Works or Concrete Pouring

FABRICATION AND INSTALLATION OF FORMS:

Type of Form-work:

The timber form-work is to be used when a limited reuse of form-work is required. As for the requirement of maximum reuse of form-work, the steel form-work is to be used.

Form-work Design:

Both types of form-work shall be designed to meet the following requirements:

Learn More 

Basic Components of Building Structure | Building Elements | Sub Structure | Super Structure

Ties:

Ties will be placed at such intervals that will not allow any movement or deformation of the formwork beyond the specified tolerance limits. Forms for small section elements, i.e, columns, shall be tied externally.
Through-ties shall be used for big area forms.

Coating:

Prior to concreting, the form shall be cleaned and any foreign material shall be removed. If necessary, openings shall be provided in the formwork for the removal of the foreign materials.
Before placing the formwork, it will be coated with the approved release agent. The properties and coating procedure shall conform to project specifications.

Removal of Forms and Shoring:

Formwork for columns, sides of beams, walls (except for tank foundations), and other formworks not supporting the concrete weight shall be removed.

Shoring and Propping:

All shoring and propping requirements shall be submitted to the client for approval.

Chamfers:

All exterior exposed corners shall be chamfered as indicated in the construction drawings.
An outline of the configuration of the system of formwork proposed to be used is given hereunder.

REINFORCEMENT:

The reinforcing steel should be conforming to project specifications and as per drawings.

Handling and stacking:

Cutting and Bending of Bars:

The reinforcement will be cut and bent in accordance with the approved bar bending schedules.
The bending of reinforcements will be done on the bending machine, producing a gradual and even motion. Bars will be bent cold and at specified radii.

Learn More 

How to Calculate the Unit Weight of Steel Bars | Bar Bending Schedule

Receipt and Storage of Bars:

Placing of Reinforcement:

Fixing of Reinforcement:

Quality Control:

The reinforcement will be inspected before concreting. It will be ensured that the surface of reinforcement will be free from mud, oil, retarders, grease, or any other substance which would affect adversely the steel or concrete chemically or reduce the bond. Also, it will be ensured that it is placed in full accordance with the issued for construction drawings.

  1. How To Estimate Per Meter Weight Of Reinforcing Steel Bar

  2. How To Calculate The Cutting Length Of Circular Stirrup

EMBEDDED ITEMS:

CONCRETING:

Transportation of Concrete:

Out of the available transit mixer trucks, at least one will be kept as stand by. Before the departure of the loaded transit mixer, the delivery ticket will be handed over to the driver.

Delivery of Concrete:

Deposition of Concrete:

Protection of Fresh Concrete:

Unless adequate protection is provided, concrete will not be placed during rain.

Curing of Concrete:

Immediately after placement, concrete will be protected from premature drying and excessively hot temperatures and will be maintained with minimum moisture loss at a relatively constant temperature for a period necessary for the hydration of the cement and hardening of the concrete.
The curing of concrete will be carried out by one of the following procedures:

  1. Pouring or a continuous sprinkling of water.
  2. The application of hessian kept continuously wet and covered with a white polyethylene sheet.
  3. The application of sand kept continuously wet.
  4. Application of waterproof sheet material subject to approval by Client.
  5. Application of curing compound subject to approval by Client.

The system to be used will depend on the nature of the structure. The above methods (2) and (5) will be mostly used.
Moisture loss from surfaces placed against wooden forms or steel forms, exposed to heating by the sun, will be minimized by draping forms with wet hessian covered with white polyethylene until they can be safely removed. After forms are removed, the concrete will be cured up to the end of the prescribed period.

Learn More 

Precautions to be Taken While Placing of Concrete | Do’s & Don’ts While Concreting

Quality Control:

Learn More

How to Calculate Cutting Length of Rectangular Stirrups And Circular Stirrups

TESTING OF CONCRETE:

SAFETY PLAN:

The safety of men and materials is a high priority for the Client. All safety measures will be observed during the entire works. Detailed safety measures for every work will be elaborated in the concerned JSA being submitted by electrical safety department to PMT HSE department, however basic account of the safety strategy is given under:

The JSA will be submitted separately by the HSSE department.

 