Site icon Surveying & Architects

Estimating Of Steel Bar Quantity for Construction

Estimating Of Steel Bar Quantity for Construction

Planning quantity for steel bars in each development is an arduous work. It needs a talented and experienced quantity assessor, estimators or engineers to make one. Each area, sub-segment, and parts of the plans with fortifying bars ought to be incorporated as missing one would be exorbitant and ruinous over the long haul.

 

 

Mat Foundation

The accompanying should help engineers on focuses to consider in deciding the strengthening bar quantity for Matt foundation.

  1. Anticipate on the off chance that it is required to utilize fortifying bars for form-works and platforms for help and strength.
  2. Check the designs for the base and top bars’ spacing, length, and width. Think about the hooks and curves on each of the two sides as planned and add it to he complete length.
  3. Inspect the arrangement for structured splicing lengths and add it to the complete length. Splicing is the connecting of two distinctive strengthening bars to accomplish the necessary absolute length.
  4. Examine the arrangement for different bars required state, seat bar. Because of the protracted tallness of mat foundation, planners use seat bars as solid spacers to isolate top bars and base bars.

Learn More

Civil Site Engineer Must Know +18 Civil Engineer Tips And Trick

 

The following is an example count for mat foundation rebar quantity.

Given

Business length per fortifying bars = 12 l.m. , (to be deducted with splicing length @ 0.8m)

Top bars

Transverse quantity = W/s= 100/0,3=333.3,say 334 pcs100 l.m.

100 + t + t = 100 + 1 + 1 = 102 l.m., 334 pcs (Additional length for hooks)

334 X 102 = 34,068 all out straight meter

(All out straight meter)/(business length-splicing)= 34,068/(12-0.8)=3,042 pcs-12meter length strengthening bars

Longitudinal quantity = L/s= 100/0,3=333.3,say 334 pcs100 l.m.

100 + t + t = 100 + 1 + 1 = 102 l.m., 334 pcs (Additional length for hooks)

334 X 102 = 34,068 all out direct meter

(All out direct meter)/(business length-splicing)= 34,068/(12-0.8)=3,042 pcs-12meter length strengthening bars

Total Quantity for TOP BARS

Transverse QTY + Longitudinal QTY = 3,042 + 3,042 = 6,084 pcs ? 12mL fortifying bars

Computing base bars is equivalent to the top bars.

Learn More

Calculation Method For Find Out The Overlapping Length Of Beam, Column And Slab

Columns

Here is a guide on deciding the quantity for strengthening bars for column.

Test computation for columns:

 

Given

W = 0.4 m

L = 1.0 m

H = 3.0 m

Primary bar pcs. = 16

Absolute number of ties = 20 pcs.

Business length of strengthening bars = 8.0 l.m.

Primary bar

Strengthening Ties

Length per ties is the border, P = 2W + 2L = 2(0.4) + 2(1.0) = 2.8 m

Absolute length = Length x No. of ties = 2.8 x 20 = 56 straight meter

Absolute number of pieces = (Total length)/(Commercial length) 56/8=7 pieces-8 meter length rebars

Slab on Grade

The accompanying methodology will help engineers on deciding the quantity of strengthening bars in slab on grade.

Sample figuring’s are given below.

Temperature bars

L = 10.0 m

W = 10.0 m

t = 0.6 m

s = 0.25 m

Business length of strengthening bars = 12.0 l.m.

Transverse bars

(same figuring for longitudinal bars since this is a square SOG)

No. of pieces = W/s= 10/0.25= 40 pieces-12 straight meter

Complete number of pieces = Transverse + Longitudinal = 40 + 40 = 80 pcs ? 12 straight meter strengthening bars

Learn More

Bar Bending Schedule For Slab And Estimation Of Steel Reinforcement In Slab

Suspended Slab

The accompanying aide should assist you with deciding the required strengthening bars for suspended slabs.

  1. Determine the tops bars spacing according to transverse and longitudinal bars.
  2. Add the hooks and splicing to the length as computed above.
  3. Any openings like steps opening ought to be deducted to the figurings.
  4. Examine the arrangement if there are twists because of progress in floor heights. Suspended slabs that are related with water are basically brought down at any rate an inch from the remainder of the whole floor like solace rooms and patios.
  5. Having been brought down, there may likewise be changes to the basic subtleties of the slabs. These curves ought to be remembered for the estimations of the strengthening bars.
  6. Add the required dowels for stone work works like dividers and solid railings on the all out quantity.
  7. Multiply the necessary rate arrangement for the wastage factor.
  8. Quantity estimation for suspended slab is actually the equivalent with the slab-on-grade and mat foundation.

Other Post

  1. How To Calculate The weight of Steel With Formula

  2. How to calculate the cutting length of reinforcement bars in circular R.C.C slab

  3. Calculation Of Staircase Concrete And Bar Bending Schedule (BBS) | Staircase Reinforcement Details

 

To get more information, Visit Our Official website
Land Surveying & Architects

JOIN US & LIKE OUR OFFICIAL FACEBOOK PAGE

THANKS.

Exit mobile version