Clicky

Home / Land Surveying / How to Calculate the RL by HI method in surveying

How to Calculate the RL by HI method in surveying

How to Calculate the RL by HI Method in Surveying.

In this article i will explain how to Calculate the RL by HI method in surveying, Let us consider an example as given below.

The leveling instrument was used to observe the subsequent readings.

0.450, 1.860, 2.755, 3.250, 3.675, 3.930, 0.885, 1.150, 1.945, 2.850, 3.635, 0.975, 1.950, & 2.585. The instrument was shifted after the Sixth and Eleventh readings. The elevation of  the first reading was 480.65m. Calculate the RL of all the points by using the Height of instrument method.

Hight of Instruments

Calculation.

 

As u can observe in the above drawing, the instrument is shifted after the Sixth and Eleventh reading.

So, first, seventh, and twelfth readings   👉 BS

Sixth, Eleventh, and 14th readings 👉  FS &

All of other remaining readings   👉  IS

Learn More

What is the Components of Road structure

How To Convert the Bearings and Distances to Coordinates

Please remember: 

👉 While Surveying, the first reading becomes BS and the last reading becomes FS.

Note: 

  •            BS  👉 backsight.

  •            FS  👉 foresight.

  •             IS  👉 intermediate sight.

  •             CP 👉  change point.

  •             HI 👉 height of instrument.

  •            RL 👉 reduced level.

Now, let us prepare the Height of the instrument table from the above-mentioned data.

Following are the rules or formulas u should remember while calculating the RL in the height of the instrument method.

1 – HI = [RL + BS]

Whenever u get the BS reading, u have to calculate the height of the instrument in that particular change point. By adding the RL to the BS u will get the HI when u establish the instrument in the new change point.

2 – RL = [HI – IS or FS]

Once the height of the instrument is calculated, u have to deduct the IS & FS from the HI to calculate the RL of that particular station. This procedure should be continued until u get the new HI at the change point.

Keeping in mind, the above given formulas, let us start the calculation procedure.

  1. First HI = [1st given RL + 1st BS] = [480.65 + 0.45]  = 481.10

  2. Second RL = [1st HI – First IS] = [481.10 – 1.860]      = 479.240

  3. Third RL = [1st HI – Second IS] = [481.10 – 2.755]     = 478.345

  4. Forth RL = [1st HI – Third IS] = [481.10 – 3.250]        = 477.850

  5. Fifth RL = [1st HI – Forth IS] = [481.10 – 3.675]         = 477.425

  6. Sixth RL = [1st HI – First FS] = [481.10 – 3.930]         = 477.170

As u can observe in the below-given table, the IS And FS is deducted from the same HI until u shift the instrument & note down the new BS reading.

Learn More

Interview Question and Answer For Land Surveying

Civil Engineering Basic Knowledge

What is The Contour Mapping

Types Of Curves In Surveying Work

Once u note down the BS reading for the change point, again u have to calculate the HI And by adding RL to the BS.

  1. Second HI = [ 6th RL  + 2nd BS] = [477.170 + 0.885] = 478.055

  2. 7th RL = [2nd HI – Fifth IS] = [478.055 – 1.150] = 476.905

  3. 8th RL = [2nd HI – Sixth IS] = [478.055 – 1.945] = 476.110

  4. 9th RL = [2nd HI – Seventh IS] = [478.055 – 2.850] = 475.205

  5. 10th RL = [2nd HI – Second FS] = [478.055 – 3.635] = 474.420

Again calculate HI for the 3rd BS

  1. Third HI = [ 10th RL  + Third BS] = [474.420 + 0.975] = 475.395

  2. Eleventh RL = [3rd HI – Eighth IS] = [475.395 – 1.950] = 473.445

  3. Twelfth RL = [3rd HI – Third FS] = [475.395 – 2.585] = 472.810

All the calculated values should be entered as shown in the below-given table.

Station

BS

IS

FS

HI

RL

Remark

1 0.450      481.10 480.650 BM
2   1.860     479.240  
3   2.755     478.345  
4 3.250   477.850
5   3.675   477.425  
6  0.885  3.930 478.055 477.170 CP1 
7  1.150 476.905
8   1.945   476.110  
9    2.850   475.205  
10 0.975 3.635 475.395 474.420 CP2
11 1.950 473.445
12 2.585 472.810
Total Ʃ 2.310   10.150    

Arithmetic check

[∑FS – ∑BS]  = [First RL – last RL] [∑FS – ∑BS] = [ 10.150 – 2.310] = 7.840 

[First RL – last RL] = [ 480.650 – 472.810] = 7.840

Hence, the calculation is the correct.

Hi Method


Other Post

How to calculate the RL of temporary benchmark on the site

Rise and fall method with Examples

How to calculate The gradient, run and rise in civil construction

How To Calculate The Asphalt Quantity For Road Work


Thanks For Reading this article. Please, Don’t Forget to Share it.

To Get More Information, Visit Our Official website
Land Surveying & Architects

JOIN US & LIKE OUR OFFICIAL FACEBOOK PAGE

THANKS.

About Raja Junaid Iqbal

Hi My name is Raja Junaid Iqbal and i am Land Surveyor by Profession but I've specialized in the field of Q,S and land development. As Professional Surveyor I engaged my self in all over the Gulf since 14 years.

Check Also

How To Convert Bearings and Distances to Coordinates

How To Convert the Bearings and Distances to Coordinates

How to Convert Bearings And Distances to Coordinates In This Article I will explain how …

error: Content is protected !!