Clicky

How To Calculate The Cement Bags Required For 2000 sq ft House

How To Calculate The Cement Bags Required For 2000 sq. ft. House

Hello guys in this article we know about quantity of bags of cement is required for 2000 square feet house. Actual quantity of cement calculation is based on as per design but if design is not given then cement quantity calculation is based on Thumb Rule on experience basis and how many cement bags used in construction of 2000 square feet house.

How to calculate the cement bags required for 2000 sq ft house

How To Calculate The Cement bags required for 2000 sq. ft. house is based on different type of criteria

1) type of structure (Load Bearing/Framed)

2) Purpose of structure (Load depends on the utility)

3) Type of grade of concrete used

4) Size height of column and length of beam (in terms of height, as requirement varies according to construction i.e. whether horizontal or vertical. )

5) Most important is foundation type(depends on soil bearing conditions)

How many cement bags required for 2000 sq. ft. house

For general residential low rise building of ground floor house we have to calculate cement bags. We use different types of Thumb Rule for cement quantity calculation in all type of RCC structure footing, column, beam & RCC slab, brickwork, flooring & plastering.

Learn More 

How To Calculate The Volume Of Concrete Triangular Pile Cap Having 3-Piles

Now taking various Thumb Rule for cement quantity calculation for 2000 square feet house

1) thumb rule for cement in RCC concrete is 0.301 cement bags/ sq. ft. built up area of low rise ground floor residential building

2) thumb rule for cement bags in surface ground flooring is 0.089 cement bags/ sq. ft. of built up area of low rise ground floor residential building.

3) thumb rule for cement bags in external wall brickwork is 1.26 cement bags/m3 of brickwork of 9 inch ( cement sand ratio 1:6)

4) thumb rule for cement bags in internal wall brick work is 1.28 cement bags/m3 of brickwork of 4.5 inch ( cement sand ratio 1:4)

5) thumb rule for cement bags for external plastering is 0.017017 cement bags/ sq. ft. plastering

6) thumb rule for cement bags for internal plastering is 0.0086 cement bags/ sq. ft. plastering

7) thumb rule for cement bags for ceiling plastering is 0.0051 cement bags/ sq. ft. plastering

How many cement bags required for 2000 square feet house ?

For the construction of residential building of ground floor we have RCC structure like footing, column, beam and slab. Taking one rough design of 2000 square feet house having different dimension of RCC structure like footing, column, beam and slab are following:

Learn More

How To Get Rid Of Common Errors In Concrete Floor Slab Construction

How many cement bags required for RCC structure of 2000 square feet house

● volume of RCC concrete calculation

1) footing size = 1500 mm × 1500mm × 300 mm

Length of footing = 1500 mm

Width of footing = 1500 mm

Height of footing = 300 mm

Depth of earth excavation = 1500 mm

Concrete size in footing = 1200mm×1200mm×300mm

No of footing = 20

Wet volume of concrete in all 20 no of footing = 1.2 m × 1.2 m × 0.3 m × 20 = 8.64 m3

2) column size = 300 mm × 400 mm

No of column = 20

Height above DPC = 3000 mm

Height above RCC slab = 900 mm

Depth of earth excavation = 1500 mm

Total height of column = 5400 mm

Wet volume of concrete for all 20 column

= 0.3 × 0.4× 5.4 × 20 = 12.96 m3

3) plinth beam size = 300mm × 300 mm

Width of beam = 300 mm

Depth of beam = 300 mm

Overall length of all beam = 400 ft. = 120000 mm

Wet volume of concrete = 0.3 × 0.3 × 120 = 10.8 m3

4) door beam size for external wall = 225mm × 150 mm

Overall length for external beam = 180 ft. = 54000 mm

Volume = 0.225 × 0.15 × 54 = 1.823 m3

Door beam size for internal wall = 125 mm × 150 mm

Overall length for internal beam = 220 ft = 66000 mm

Volume = 0.125 × 0.15 × 66 = 1.238 m3

Total volume of concrete = 1.823 + 1.238 = 3.061 m3

5) roof wall beam size for external wall = 225 mm × 200 mm

Overall length for external beam = 180 ft. = 54000 mm

Volume = 0.225 × 0.2 × 54 = 2.43 m3

Roof wall beam size for internal wall = 125 mm × 200 mm

Overall length for internal wall beam = 220 ft. = 66000 mm

Volume = 0.125 × 0.2 × 66 = 1.65 m3

Total volume = 2.43 + 1.65 = 4.08 m3

6) RCC roof slab = 50′ × 40’×6″

Length of slab = 50 feet

Width of slab = 40 feet

Thickness of slab = 6 inch = 0.5 feet

Volume = 50′ × 40’× 0.5′ = 1000 cubic feet

1 m3 = 35.3147 cu ft.

Volume = 1000/35.3147 = 28.32 m3

 

Now Total wet volume of concrete required for 2000 square feet house

Footing = 8.64 m3

Column = 12.96 m3

Plinth beam = 10.8 m3

Door beam = 3.06 m3

Roof beam = 4.08 m3

Roof slab = 28.32 m3

Total wet volume of concrete = 67.86 m3

Dry volume of concrete = 67.86 ×1.54 = 104.5 m3

If we take M20 grade of concrete in which cement sand and aggregate ratio is 1:1.5:3

Cement quantity = (1/5.5)× 104.5m3 × 1440 kg/m3

Cement weight = 27361 kg

1 cement bag weight = 50 kg

no of cement bags = 27361/50 = 547.2

Learn More

How to Create The Design Of RCC Structures With Details

547.2 no of cement bags required for RCC concrete structure footing, beam, column & slab for 2000 sq ft house of low rise building of ground floor.

Cement bags required for brickwork of 2000 square feet house

1) cement consumption in external brick wall

External brick wall length = 2(50+40) = 180 ft

Height of brick wall = 10 feet

Height of brick wall above roof slab = 3 feet

Depth of brick wall below plinth = 2 feet

Total height = 15 feet

Area of external brick wall = 180×15 = 2700 sq. ft.

Volume = 2700 sq. ft. × 9 inch = 2025 cu ft.

Volume = 2025/35.3147 = 57.43 m3

Volume of brickwork = 57.34 m3

Thumb rule for cement bags in external wall brickwork is 1.26 cement bags/m3 of brickwork of 9 inch ( cement sand ratio 1:6)

no of cement bags = 57.34 × 1.26 = 72.25 bags

2) Cement consumption in internal brick wall

brick wall length = 50+50+40+40 + 40= 220 ft.

Height of brick wall = 10 feet

Depth of brick wall below plinth = 2 feet

Total height = 12 feet

Area of external brick wall = 220×12 = 2640 sqft

Volume = 2640 sq. ft. × 4.5 inch = 990 cu ft.

Volume = 990/35.3147 = 28 m3

Volume of brickwork = 28 m3

Thumb rule for cement bags in internal wall brickwork is 1.28 cement bags/m3 of brickwork of 4.5 inch ( cement sand ratio 1:4)

no of cement bags = 28 × 1.28 = 36 bags

Total no of cement bags = 72.25 + 36 = 108.25

108.25 no of cement bags required for brickwork of 2000 square feet house

Learn More

Methods of Concrete Column Repair for Damages and Cracks

How many cement bags required for ground flooring of 2000 square feet house.

In ground flooring we use plain cement concrete m15 grade of concrete in which mix ratio of cement sand and aggregate is 1:2:4 and floor thickness is 6 inch ( 4 inch concrete + 2 inch paltering for flooring + tile flooring)

Ground flooring concrete slab = 50′ × 40’×6″

Length of slab = 50 feet

Width of slab = 40 feet

Thickness of slab = 6 inch = 0.5 feet

Volume = 50′ × 40’× 0.5′ = 1000 cubic feet

1 m3 = 35.3147 cu ft.

Volume = 1000/35.3147 = 28.317 m3

Wet volume = 28.317 m3

Dry volume = 28.317 × 1.54 = 43.60 m3

no of cement bags = (1/7) 43.60 × (1440/50)

no of cement bags = 179 bags

179 no of cement bags required for ground flooring of concrete, plastering of ground flooring and tile flooring of 2000 square feet house

How many cement bags required for plastering of 2000 square feet house

1) External plastering of brick wall

Length total = 180 ft.

Height = 10 ft.

Area of plastering = 180 × 10 = 1800 sq. ft.

thumb rule for cement bags for external plastering is 0.017017 cement bags/ sq. ft. plastering

no of cement bags = 1800 × 0.017017 = 30.6 bags

2) internal plastering of brick wall

Length total = 620 ft.

Height = 10 ft.

Area of plastering = 620 × 10 = 6200 sq. ft.

thumb rule for cement bags for external plastering is 0.0086 cement bags/ sq. ft. plastering

no of cement bags = 6200 × 0.0086 = 53.32 bags

3) ceiling plastering of roof slab

Length total = 2000 ft.

thumb rule for cement bags for ceiling plastering is 0.0051 cement bags/ ft. plastering

no of cement bags = 2000 × 0.0051 = 10.2 bags

Total no of cement bags = 30.6+ 53.32 + 10.2 = 94

94 no of cement bags required for external wall plastering, internal wall plastering and ceiling plastering of 2000 square feet house

Learn More

What is Concrete Discharge Time Requirements

Now total number of cement bags required for 2000 square feet house

1) R.C.C Concrete = 547.2 bags

2) Brickwork = 108.25 bags

3) Flooring + Septic tank + stair = 179 bags

4) Plastering = 94 bags

Total no of cement bags = 928.45 = 929

929 (+ 5% and _ 5℅ shift) no of cement bags ( 547.2 cement bags for RCC concrete, 108.25 cement bags for brickwork, 179 cement bags for flooring, septic tank including stair & 94 cement bags for plastering) are required for construction of 2000 square feet house of low rise ground floor building.

This is a general guidelines and actual quantity of steel may vary for special design.

Other Post 

  1. What is Sprayed Concrete in Concrete Construction

  2. Layout Procedure Of The Building Footings


To get more information, Visit Our Official website
Land Surveying & Architects

JOIN US & LIKE OUR OFFICIAL FACEBOOK PAGE

THANKS.

About Raja Junaid Iqbal

Hi My name is Raja Junaid Iqbal and i am Land Surveyor by Profession but I've specialized in the field of Q,S and land development. As Professional Surveyor I engaged my self in all over the Gulf since 14 years.

Check Also

Segregation and Bleeding in Concrete

Segregation and Bleeding in the Concrete

Segregation & Bleeding in the Concrete | Causes, Effects And Remedies Segregation in concrete Segregation …

Leave a Reply

Your email address will not be published. Required fields are marked *

error: Content is protected !!